most suitable kind under the conditions to be complied

with.

207

20.

It is intended to carry out the work by contract,

the estimated period required for construction being from

five to six years.

21.

It is apprehended by the local authorities,that

shoaling to any serious extent will not occur within the

enclosed area, that opinion having apparently been based

on the fact, that the water on the site of the works is

clear and free from matter in suspension. No current

observations are available which are sufficient to enable

us to consider this aspect of the case as applicable to

the enclosed area generally, but we may observe that some

shoaling may certainly be anticipated along the line of the

frontage of the Harbour, seaward of the allotments, due to

detritus brought down by heavy rains through the sewers,

as was the case in front of the old Praya, and which

action we believe is now going on in front of the more

recent work there.

Such accretions will necessitate

--10--